Suceeding Where All Else Failed ...



How ACF overcame multiple adversities in building a large-scale tidal regulator in Gujarat.



Farmers in Kodinar were scared, and the future looked bleak.  They were losing hope for their livelihoods - after all salinity had been a problem since 1970.



An attempt by Government in 1986 to install 30 'tidal regulator' steel gates was a complete failure.  The gates stood there corroding - a constant reminder of the ever-creeping tide.



Taking matters into their own hands, community members tried to revive a local check dam - but despite hard work, significant cost and best intentions, the problem persisted.



In 2002, they approached the local MLA and finally in 2008 a tender was issued to solve the salinity problem - won by a local contractor, who immediately started work.



But farmers were not convinced - they had seen the work of this contractor and the quality was poor.



Meanwhile, Ambuja Cement Foundation had been working with the government on other projects and was requested to take over the INR 8.516 Million project.



Challenges, however, continued to thwart the project.  The aim was to build a spillway in place of the regulator gates - but when excavation began, water was seeping in quicker than it could be removed.  



Putting their heads together, ACF staff decided to build a temporary earthen bund downstream, to prevent the barrage of water from the sea.  But once, twice, three times, the bund gave way and collapsed.



Many others in their place, would have offered defeat - was this an 'impossible project?'  But being local to the area, the team summoned their determination - their peers, friends and communities depended on it.



And in 2009 the project was completed in just 5 months.  And today, crops bloom, profits abound and the health and happiness of the region has returned once more.



After decades of others trying, ACF succeeding in reversing the tide. But that's just one piece of the puzzle. ACF's water management efforts in Kodinar have returned a 13 times social return on investment.

ACF helped 2363 farmers embrace drip irrigation, constructed 218 check dams, 1268 recharge wells and 114 ponds. They interlinked rivers, helped install 3833 rooftop rainwater harvesting systems and converted mined out pits into water storage facilities - pushing salinity back to the shore across a 60km stretch of the coast.